(Created page with "Attendees: == ECP Updates == * KPP-3 ** ParaView/VTK-m KPP3CP work is done. Need to submit. Maybe we can copy stuff Eric is doing for VisIt. Setting a target deadline for A...")
 
 
(2 intermediate revisions by the same user not shown)
Line 1: Line 1:
Attendees:  
+
Attendees: Ken Moreland (ORNL), Mark Bolstad (SNL), Hank Childs (UO), Roxana Bujack (LANL), Ollie Lo (LANL), Manish Mathai (Kitware), Terry Turton (LANL), Silvio Rizzi (ANL), Sujin Philip (Kitware), Abhishek Yenpure (Kitware), Tushar Athawale (ORNL), Jay Wang (ORNL), Dave Pugmire (ORNL), Berk Geveci (Kitware), Nicole Marsaglia (LLNL), Vicente Bolea (Kitware), Jeff Amstutz
  
 
== ECP Updates ==
 
== ECP Updates ==
Line 13: Line 13:
 
** Based on KPP-3 work
 
** Based on KPP-3 work
 
* R&D 100 Submission
 
* R&D 100 Submission
 +
* Frontier moving to general access April 3
  
 
== Porting Activities ==
 
== Porting Activities ==
  
 
* https://wiki.jlse.anl.gov/display/inteldga/ECP+2.3.4.13+VTK-m
 
* https://wiki.jlse.anl.gov/display/inteldga/ECP+2.3.4.13+VTK-m
* https://confluence.exascaleproject.org/display/STDA05/Porting+Activities+O21
+
* https://confluence.exascaleproject.org/display/STDA05/Porting+Activities+Frontier
  
 
== ECP task updates ==
 
== ECP task updates ==
Line 24: Line 25:
  
 
== Roundtable ==
 
== Roundtable ==
 +
 +
Jim strongly encouraging having the DAV portfolio for running KPP3CPs on Frontier.
 +
 +
Going to refactor the ANARI work to be more interop based.
 +
 +
Dave moving rendering things from VTK-h to VTK-m. Started by moving VTK-h rendering wholesale in VTK-m. It works, but needs to fix the interface to work correctly.

Latest revision as of 13:17, 29 March 2023

Attendees: Ken Moreland (ORNL), Mark Bolstad (SNL), Hank Childs (UO), Roxana Bujack (LANL), Ollie Lo (LANL), Manish Mathai (Kitware), Terry Turton (LANL), Silvio Rizzi (ANL), Sujin Philip (Kitware), Abhishek Yenpure (Kitware), Tushar Athawale (ORNL), Jay Wang (ORNL), Dave Pugmire (ORNL), Berk Geveci (Kitware), Nicole Marsaglia (LLNL), Vicente Bolea (Kitware), Jeff Amstutz

ECP Updates

  • KPP-3
    • ParaView/VTK-m KPP3CP work is done. Need to submit. Maybe we can copy stuff Eric is doing for VisIt. Setting a target deadline for April 3.
    • We are in queue to use Frontier this week, but it is not looking likely
  • Budget estimations for FY24
    • Asking for 1/4 of FY23 spend plan for FY24Q1
      • Was told by Jordan Williams that should not be an issue
    • Trying to make sure contracts continue
  • Highlights
    • Based on KPP-3 work
  • R&D 100 Submission
  • Frontier moving to general access April 3

Porting Activities

ECP task updates

ECP/VTK-m Project Management

Roundtable

Jim strongly encouraging having the DAV portfolio for running KPP3CPs on Frontier.

Going to refactor the ANARI work to be more interop based.

Dave moving rendering things from VTK-h to VTK-m. Started by moving VTK-h rendering wholesale in VTK-m. It works, but needs to fix the interface to work correctly.