Teleconference 2023-06-07
Jump to navigation
Jump to search
Attendees:
ECP Updates
- KPP-3
- MFiX KPP3CP work is done. We should start writing up the submission.
- Budgets for FY24/Q1 sent to Jordan Williams
- I have been told that subcontracts are expected
- Asked for 1500 hours on Summit for Q4 in case you need it
- Highlights
- Based on KPP-3 work
Porting Activities
- https://wiki.jlse.anl.gov/display/inteldga/ECP+2.3.4.13+VTK-m
- https://confluence.exascaleproject.org/display/STDA05/Porting+Activities+Frontier
ECP task updates
Roundtable
No meeting next week. Ken will be unavailable during the entire week.
It was brought up that it would be nice to do an in person hackathon. After some discussion, there was some thought that it would be nice to meet at ANL over the summer. Silvio will look into logistics.