Attendees: Ken Moreland (SNL)
ECP Updates
- Thanks to Hank for getting KPP-3 integration metric done
- Final Design Report section submitted
- Starting to plan work detail for FY20 and beyond
- Basis of Estimate due May 1
- Basically need to provide budgets for FY20-23.
- Need to work with your financial people.
- Last chance to decide on subcontracts.
- We have been given lump sums for FY20 and FY21-FY23
- Ken will provide divisions among institutes shortly
- Lump sum includes a 9% decrease per year decrease
- Projects that deal with porting (our project was called out) should actually use more funds in the later years.
- Next steps
- Ken will assign money to each institution
- All PIs will report their breakdown of budget per year
- Each PI will work with their budget persons to fill out spreadsheet forms
- Questions to ask Mike:
- Is there a way to transfer FY20 funds to later (carryover)?
- Do non-labs submit their own budget or should it be included in the lab holding the subcontract?
- Review confluence page: https://docs.google.com/document/d/1L44kTtwKi0SgeSJxt62OGGI7hpfpte-OHm0V0B6vsg8/edit#heading=h.hk0so9awvgd1
- Budget pages: https://confluence.exascaleproject.org/download/attachments/61904390/BOE%20CD-2.xlsx?version=1&modificationDate=1554499415120&api=v2
- Basically need to provide budgets for FY20-23.
ECP deliverable updates
FY19Q3
- [MS-19/08] Point Movement 2
- There are already some filters in for point movement.
- Still need some user's guide documentation
FY19Q4
- [MS-19/09] Path Geometry
- Not started
- Some of the functionality is already there
- [MS-20/01] Lightweight Cell Library
- Been doing some changes on the interface to the VTK-m cell library.
- Most of the underlying library is ready.
- Almost ready.
- Still need to implement VTK-m data around it.
- [MS-20/02] Specialized Data Models
- Some work on how XGC used a rotated triangular grid for a bunch of wedges.
- Need to generalize some code written by Matt.
- Pulling in code from other contributors.
- Connect up with Berk who is picking up XGC work from before.
- Need to brainstorm on what other features would be useful.
- [MS-20/03] Feature-Sensitive Surface Norm
- First pass in a MR
- Need to wait until CUDA 8 off all dashboards
- Should be walking the graph traversal
- First pass in a MR
- [MS-20/04] VTK-m Release 3
- On track
- Probably June would be a good time for a release.
- [MS-20/05] Cell Metrics
- Progress seems a bit slow.
- Will make a sprint during the Spring semester
- [MS-20/06] Contouring
- Ollie looking into VTK implementation and flying edge paper.
- [MS-20/07] Advanced Flow Algorithms
- Merged in fix to do double precision correctly.
- Still deciding what we want to do.
- Planning on talking during DOECGF
- Hybrid parallel seems like a good way to go
- Dave is working on generalizing cell lookups and evaluators to work on all grid types
Rountable notes
We should try to collect some ECP data so that as we do reporting we can quickly generate relevant images. It would be great if we could also share across ALPINE and other vis projects.
- Terry Turton has collected some stuff from LANL. Not sure if can be sent out.
- She might have a list of distributed data in different places
There have been some code checked in that does not follow VTK-m coding styles (such as member variables not being capitalized, always using this pointer). We should be more vigilant during code reviews.
There are some new warnings on the dashboard. Are those in the process of getting fixed?
Hackathon?