Teleconference 2023-02-22

From VTKM
Revision as of 17:52, 20 February 2023 by Kmorel (talk | contribs) (Created page with "Attendees: == ECP Updates == * Summit allocations ** There will no longer be automatic Summit allocations for ECP ** If we need Summit access for FY23/Q3, we must submit an...")
(diff) ← Older revision | Latest revision (diff) | Newer revision → (diff)
Jump to navigation Jump to search

Attendees:

ECP Updates

  • Summit allocations
    • There will no longer be automatic Summit allocations for ECP
    • If we need Summit access for FY23/Q3, we must submit an allocation request by March 1
    • Do we have any need/desire for Summit access?
  • KPP-3
  • Update P6 Activity
  • Budget estimations for FY24
    • Asking for 1/4 of FY23 spend plan for FY24Q1
      • Was told by Jordan Williams that should not be an issue
    • Trying to make sure contracts continue
  • Highlights
    • Based on KPP-3 work

Porting Activities

ECP task updates

ECP/VTK-m Project Management

Roundtable

Bronson Messner approached Ken asking if VTK-m could do a KPP-3 run on Frontier (that did not need to stress the file system). After some discussion, it made sense to run the In Situ benchmark on a lot of processes. The benchmark needs to be fixed for MPI run. The two items to fix are a correct parallel rendering (image composite/reduction) and a correct partitioning of the input. Once that is done, it should be trivial to run the small program at scale.

Decided on doing 4 "early" KPP-3 metrics

  • Flow for WarpX and/or WDMApp
    • Springboard off Abhishek's thesis work
  • Ascent integration
  • ParaView integration
  • VisIt integration

R&D100?

  • Thinking of submitting for 2023
  • Big stumbling block: needs to be "created" between Jan 2022 to March 2023
  • Plan: Release VTK-m 2.0, do a copyright assertion